PETKIM CHLORINE ALKALI PLANT

PROJECT OVERVIEW
EMPLOYER
Petkim Turkish State Petrochemical Co.
LOCATION
Izmir/Turkey
PROJECT DETAILS

Turnkey construction of chlorine alkali plant with 75,000 ton/year chlorine, 84,000 ton/year caustic soda, 9,500 Ncm/day hydrogen, 7,700 ton/year sodium hypochlorite capacity; including construction, structural steel manufacturing and erection, equipment erection, mechanical, electrical and instrumentation works and commissioning.
The scope of contract covered; 2,300 m piling, 135,000 m3 earthworks, 47,000 m2 formwork, 29,000 m3 concrete, 1,500 ton precast concrete, 22 atmospheric tanks (794 ton) and 1,250 ton structural steel manufacturing and erection, 40,800 m piping and 2,000 ton equipment erection, 2,200 units of instrumentation, 50,000 m2 painting, equipment and pipe insulation. Process columns with overall weight 810 ton two of those with agitators (8m dia., 40 m height and 170 ton weight.)
Process design and engineering: Oronzio de Nora/Italy - Catalytic International/England