Turnkey construction of a 2.628 m3/day isomerization unit, including; construction, structural steel manufacturing and erection, piping, mechanical, electrical and instrumentation, equipment supply and erection, construction of administration and laboratory buildings and firefighting system.
The scope of contract covered; 1.000 ton equipment erection, 2.500 ton structural steel manufacturing and erection, 200 ton piping manufacturing and erection.
The project is executed in a consortium with Tecnicas Reunidas/Spain. Entes was responsible for civil works and all erection. Engineering and equipment supply by Tecnicas Reunidas.
Financing : Spanish Exim Bank